Traffic Updates

Our construction team will be working on Stanford Street between W Mckinney Street (see map below). Allen Pkwy will be open, but through traffic will not be able to travel north on Stanford St. to Allen Pkwy. During this closure traffic will only be able to turn left on Stanford Street from W. Mckinney and Buffalo Terrace.

UPCOMING

PHASE 1

Phase I will resume the week of April 1 and is anticipated to be complete by April 12.
Road Closure Updates: Allen Pkwy will be open, but through traffic will not be able to travel north on Stanford St. to Allen Pkwy.

PHASE 2

Phase II will resume once Phase I is complete.

PHASE 3

This Phase is mostly complete and will be finished following repaving in 4 – 6 weeks.

Note all dates are subject to change, weather permitting.